Meeka Metals (ASX:MEK) has announced major advancements in its Murchison Gold Project for November 2024. The company is expanding its CIL gold processing plant and has nearly completed a new accommodation village. Open pit mining is set to begin in March 2025, with gold production expected by mid-2025.
Meeka Metals is making significant headway in its Murchison Gold Project, aiming for first gold production by mid-2025. The company has completed key infrastructure developments like the CIL gold processing plant expansion and is finalizing accommodations for workers. Open pit mining is scheduled to start in March 2025, with contract negotiations nearing conclusion. They are also advancing various drilling programs and infrastructure projects, including a haul road. An updated Definitive Feasibility Study will be released in December 2024. Meeka Metals is focused on enhancing its operational capabilities and has outlined strong financial projections for the project.
The reinforcement and formwork for the ball mill foundation have been completed and concrete has been poured. Foundations for leach and adsorption tanks have been poured, and tank skin fabrication is underway.